Construction Dates: Summer 2008-Spring 2010
Details: The Gas Turbine #10 project will be located in the Power Plant Annex building (PPA) on 24th Street just west of San Jacinto Street. The new unit will replace an existing gas turbine and boiler.
Benefits to Campus: Electrical generating capacity will be increased at this site from 14 MW to 32 MW, bringing the campus total capacity to about 140 MW.
Contacts: If you have questions about construction of Gas Turbine #10 or about the goals of the project, contact Al Schuman, associate director of Utilities and Energy management, at 512-471-4467.
Construction Dates: Spring 2009-Spring 2010
Details: The Thermal Energy Storage project will be located in the F26 parking lot, just north of the San Jacinto Garage. A 100-foot diameter by 75-foot-high tank containing more than four million gallons of chilled water will be installed, supporting about a 41,000-ton-hour capacity.
Benefits to Campus: The tank will add capacity to the campus cooling system, allowing for increased overall efficiency.
Contacts: If you have questions about construction of the Thermal Energy Storage tank or about the goals of the project, contact Al Schuman, associate director of Utilities and Energy management, at 512-471-4467.