The University of Texas at Austin

ITS Services Status

Current Service Interruptions

1/28/2015
2:39 PM
RESOLVED: Intermittent Toopher two-factor authentication issues & Slowdowns
Service Restored

01/28/2015 2:36 pm
All issues have been addressed and the two-factor authentication system is operating normally at this time.


01/28/15 11:47 am
The vendor has implemented a fix to address the SMS issue and is investigating the other reported issues. 


01/28/15 10:32 am
At approximately 10:15 AM the two-factor authentication protecting all Payroll and W-2 information has sporadically been unable to pair customers using SMS or the Toopher application.
This means that some customers are not able to pair for the first time using SMS or the mobile Toopher application nor are some customers able to authenticate despite already being paired.
At this time we do not know of anyone having trouble authenticating or pairing using the OTPs.

The two-factor system is functioning in a degraded state but ITS is aware and working to resolve the issue.


01/28/15 10:31 am
The Toopher two-factor authentication system is experiencing intermittent issues affecting customers that use the SMS texting option. Vendor support has been engaged.

1/28/2015
11:58 AM
RESOLVED: COM4 slowdown
Service Restored

01/28/15 11:56 am
The issue causing the slowdown has been addressed and COM4 is back to normal.


1/28/15 11:45 am
The Develop instance of COM-PLETE is experiencing slowdowns, primarily in the Test and Qual environments.  Systems staff are investigating.

1/28/2015
10:42 AM
RESOLVED: Small number of emails from mainframe delayed
Service Restored

1/28/15 10:30am
The 67 delayed emails were sent out at 10:23 am today.


1/28/15 9:10am
Please consider this issue closed.

One (suspected junk) mail in particular caused a delay for about 60 messages, but this particular mail process is an offline/batch process with no strict delivery timeline.  The ~60 delayed messages will be sent by 11:00 AM today.

No real-time emails were affected and batch processing emails are going out normally at this time.


1/27/15 7:24pm
A small number of emails sent out from the UT mainframe via a “batch” email program (EMN$MAIL) are delayed.
ITS Systems staff are investigating.

1/28/2015
7:24 AM
RESOLVED: CATV Outage
Service Restored

1/28/2015 7:18am
This problem was resolved at about 1125 yesterday morning.


1/27/2015 11:21am
We are experiencing an outage on the CATV system.  We are working to restore service.

Past Service Interruptions

Upcoming Maintenance

<<< 09/29/2013 - 10/19/2013 >>>
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
29

12:00 AM - Blackboard Weekly Maintenance

12:00 AM - Austin Exchange Message Service (AEMS) Planned Maintenance

12:00 AM - Austin Disk Services Planned Maintenance Window

12:01 AM - SharePoint 2010 Maintenance

9:00 AM - VM storage migrations to permit SAN OS upgrades

6:00 PM - ArcGIS/Matlab License Server Outage

30

9:00 AM - VM storage migrations to permit SAN OS upgrades

1

7:00 AM - XML Gateway PROD - prep for UTLogin transition

8:00 AM - UDC-C Cooling Tower #1 & #2 Planned - Non-Disruptive Maintenance

9:00 AM - VM storage migrations to permit SAN OS upgrades

4:00 PM - ERP Web Infrastructure Maintenance Window

10:00 PM - Web Central Scheduled Maintenance

2

6:00 AM - UTLogin routine maintenance

7:00 AM - XML Gateway PROD - prep for UTLogin transition

7:00 AM - MySQL (non-CAT1) database outage (mysqldb.its.utexas.edu)

8:00 AM - UDC-C Cooling Tower #1 & #2 Planned - Non-Disruptive Maintenance

9:00 AM - VM storage migrations to permit SAN OS upgrades

9:00 AM - University Directory ( White Pages ) Maintenance

5:00 PM - Blog Service Weekly Maintenance

5:00 PM - DEFINE Internals/Enterprise Workflow Planned Maintenance

6:00 PM - A2 Patch implementation

9:00 PM - OS Patching of Document Repository production servers

10:00 PM - UT Lists planned maintenance

3

7:00 AM - XML Gateway PROD - prep for UTLogin transition

8:00 AM - UDC-C Cooling Tower #1 & #2 Planned - Non-Disruptive Maintenance

9:00 AM - VM storage migrations to permit SAN OS upgrades

4

7:00 AM - XML Gateway PROD - prep for UTLogin transition

8:00 AM - UDC-C Cooling Tower #1 & #2 Planned - Non-Disruptive Maintenance

9:00 AM - VM storage migrations to permit SAN OS upgrades

5

6:00 AM - Footprints Weekly Maintenance

7:00 AM - XML Gateway PROD - prep for UTLogin transition

9:00 AM - VM storage migrations to permit SAN OS upgrades

6

12:00 AM - Blackboard Weekly Maintenance

12:00 AM - Mainframe maintenance window

12:00 AM - Austin Exchange Message Service (AEMS) Planned Maintenance

12:00 AM - Austin Disk Services Planned Maintenance Window

7:00 AM - XML Gateway PROD - prep for UTLogin transition

9:00 AM - VM storage migrations to permit SAN OS upgrades

7

7:00 AM - XML Gateway PROD - prep for UTLogin transition

9:00 AM - VM storage migrations to permit SAN OS upgrades

3:30 PM - PyPE OS Security Patching - Test & Qual

4:30 PM - DEFINE Internals/Enterprise Workflow Expedited Non-Disruptive Maintenance

8

7:30 AM - VPN Maintenance

9:00 AM - VM storage migrations to permit SAN OS upgrades

2:00 PM - Planned DPUSER Maintenance in PROD

9

9:00 AM - VM storage migrations to permit SAN OS upgrades

9:00 AM - uTexas Enterprise Directory (TED) routine maintenance

9:30 AM - Javamail, FTPMail Qual and Test host patching

5:00 PM - Blog Service Weekly Maintenance

10

9:00 AM - VM storage migrations to permit SAN OS upgrades

9:00 AM - Shibboleth Maintenance

10:30 AM - Planned Apollo Maintenance in PROD

2:00 PM - uTexas Enterprise Directory (TED) - Expedited Non-Disruptive

11

7:00 AM - Data Center Cleaning Expedited - Non-Disruptive

9:00 AM - VM storage migrations to permit SAN OS upgrades

5:00 PM - AEMS Office 365: Load balancer change for authentication servers

12

6:00 AM - Footprints Weekly Maintenance

9:00 AM - VM storage migrations to permit SAN OS upgrades

13

12:00 AM - Blackboard Weekly Maintenance

12:00 AM - Austin Exchange Message Service (AEMS) Planned Maintenance

12:00 AM - Austin Disk Services Planned Maintenance Window

12:01 AM - SharePoint 2007 Security Update

9:00 AM - VM storage migrations to permit SAN OS upgrades

14

7:15 AM - Mainframe Green Output destination changing to Austin Disk

9:00 AM - VM storage migrations to permit SAN OS upgrades

15

6:00 AM - VoIP System Patch

6:30 AM - PROD uTexas Identity Manager (TIM) Routine Maintenance

9:00 AM - VM storage migrations to permit SAN OS upgrades

4:00 PM - ERP Web Infrastructure Maintenance Window

6:00 PM - Wiki Service Monthly Maintenance

16

9:00 AM - VM storage migrations to permit SAN OS upgrades

9:30 AM - Javamail, FTPMail PROD quarterly OS patching

5:00 PM - Blog Service Weekly Maintenance

5:00 PM - DEFINE Internals/Enterprise Workflow Planned Maintenance

17

9:00 AM - VM storage migrations to permit SAN OS upgrades

1:00 PM - Urchin Planned Maintenance Window

18

9:00 AM - VM storage migrations to permit SAN OS upgrades

10:00 PM - SharePoint 2010 Maintenance

19

6:00 AM - Footprints Weekly Maintenance

7:00 AM - WebSpace planned database maintenance

9:00 AM - VM storage migrations to permit SAN OS upgrades


  No maintenance to be scheduled
  Today's date

We Can Help

Get help from an expert:

* ITS Help and Service Desk

* Call us at 512-475-9400

* Submit a help request online

We also have a walk-in service in the first floor lobby of the Flawn Academic Center (FAC). Stop by and let us help you!