Rerouting Cables When Rearranging Office Space

The ITS Business Office has established new guidelines for scheduling the rerouting of cable.  If you are planning to rearrange your office space and will need cabling rerouted, please take the following lead times into consideration when contacting the ITS Business Office:


  • Two weeks’ notice prior to moving small amounts of cable

  • Three weeks’ notice prior to moving large amounts of cable

Please note that an additional week of lead time is required between May 1 and October 1, as more moves are scheduled during this period.

More information about scheduling the rerouting of cable can be found on the Cabling and Wiring site.