08CSP017.1 - CBA - PROJECT A-CIBER OFFICE SUITE RENOVATIONS 08CSP017.2 - CBA - PROJECT B-FCC-UPO RENOVATIONS
Project Summary
This Project Proposal includes the following project:
PROJECT A
CIBER Office Suite Renovations
College of Business Administration (CBA)
Approximately 1,400 SF project area. Abate floor tile/mastic (<250 SF Contiguous area), demolish interior construction of existing rooms, including specified architectural, electrical, mechanical, fire sprinklers, fire alarm system, & reconstruct per CDs.
PROJECT B
FCC-UPO Renovations
College of Business Administration (CBA)
Approximately 1,935 SF project area. Demolish interior construction of existing office suite, including specified architectural, electrical, mechanical, fire sprinklers, fire alarm system, . reconstruct per CDs. No ACM involved.
The general Construction Budget for each project is approximately:
Project A: $117,000.00 to $133,000.00
Project B: $166,000.00 to $188,000.00
Project Site
College of Business Administration
Key Dates:
- Pre-Proposal Conference Site: FC1, Room 1.118C
- Specifications and Plans Available on or about: March 25, 2008
- Notice to Proposals Out: March 20, 2008
- Pre-Proposal Date: March 27, 2008 Time: 10:30 A.M.
- Envelope #1 Date: April 10, 2008 Time: 2:00 P.M.
- Envelopes #2 & #3 and Public Opening Date: April 11, 2008 Time: 2:00 P.M.
(All proposal envelope openings held at FC1, Room 2.102. See map below.) - No. of Addenda: 0
PMCS Offices:
Directions to PMCS:
FC1 - Facilities Complex Building 1, 1301 E. Dean Keeton, Austin (Corner of Dean Keeton and Lafayette St.)
From the South: Take the Manor Rd. exit and continue north through the light passing Mt. Calvary cemetery on the right. Turn right at the LBJ Library sign and stay to the left. The Facilities Complex is just across Dean Keeton. Turn left. At the second driveway, turn right.
From the North: Take the Manor Rd exit. Turn left at Manor Rd. then left again onto the frontage road. Continue north, passing Mt. Calvary cemetery on the right. Turn right at the LBJ Library sign and stay to the left. The Facilities Complex is just across Dean Keeton. Turn left. At the 2nd driveway, turn right.