Facility Renovation Memorandum
November 28, 2001
| To: |
All University Clients of Physical Plant |
| From: |
Sheldon Ekland-Olson, Executive Vice President and Provost
Pat Clubb, Vice President for Employee and Campus Services |
| Subject: |
Procedures for Requesting Renovation Projects |
This memorandum outlines updated procedures and schedules for campus renovation
projects as part of Physical Plants continuing effort to improve and streamline
the management of these projects. These projects include but are not limited
to office, laboratory, and classroom renovations, and interior renovations that
involve new furniture and carpet. The procedures to request routine maintenance
are unchanged and these requests should continue to be transmitted directly
to your Physical Plant Zone Maintenance Office.
Physical Plant is now responsible for the design and management of renovation
projects with budgets up to $2,000,000, an increase from the previous cap of
$600,000. Since these larger projects demand more design and construction time
than smaller projects, they will require earlier submittal to ensure timely
project delivery. Physical Plant will continue to evaluate its current project
delivery system to improve its capacity to accommodate these larger projects.
In addition, to meet this increased demand and to help address the existing
design backlog, Architectural and Engineering Services Division (A&E) of
Physical Plant recently established open-ended contracts with several design
firms, enabling more projects to be designed each year.
In our efforts to continue to improve our service and to help Physical Plant
to better meet your needs, the following information and guidelines are provided
to assist you as you submit projects.
INITIATION OF NEW RENOVATION PROJECTS
Step 1: Identify project and submit work request [PP10]
As the first step to initiate a new renovation project, the client
must identify the scope of work and submit a request for preliminary
design and cost estimate using a work request form [PP-10]. Work
Request forms are available on the Physical
Plant web page. Select "PP10 Order Forms (PDF)" from
the list at the top of the page.
Academic departments and non-academic units must submit the PP-10 request for
preliminary design and cost estimates to their Deans or Vice Presidents
office. The Dean or Vice President should assess the validity and scope of the
proposed project, determine its relative priority, and forward only those projects
that are clearly important to enhance their programmatic goals to the Planning
and Construction Division (P&C) at Physical Plant. A careful screening at
this stage will permit the University to make optimal use of limited resources
and ensure that Physical Plant dedicates estimating and design resources to
projects which best serve the University.
Step 2: Preliminary Design and Cost Estimate
The second step is the development of a preliminary design and cost estimate
by Physical Plant. Generally, first priority for Physical Plant estimating and
design resources as well as project execution resources is assigned to faculty
recruiting requests. Second priority is assigned to requests for preliminary
design and cost estimates for renovation projects critical to the development
of new initiatives and/or the continuation of existing programs. Third priority
is assigned to all other routine projects.
Step 3: Authorization for Construction
The third step and final step in the process is authorization for construction,
which involves formal approval of the project and identification of the funding
source by the client. All client questions pertaining to funding of the project
shall be directed to the Provost or the respective Vice President. Academic
departments should submit requests for construction authorization, accompanied
by all the preliminary design and cost estimate materials, via their respective
Dean to the Provost. Non-academic units should submit their requests to their
respective Vice President. The Dean or Vice President should re-assess the project
and decide if the project should be approved for construction. If the project
is approved, the Provost or Vice President should determine the overall priority
for the project within their operating unit. Academic departments must
comply with Provost procedures regarding funding and project scope approval.
Special expediting or other unusual handling of proposed academic and non-academic
construction projects requires the approval of the Provost or Vice President
for Employee and Campus Services. Since project estimating resources as well
as design and construction resources are finite, approval of a request to expedite
a project will usually require deferring other projects currently in progress.
The Provost and Vice Presidents have final responsibility for the approval
of renovation projects. For certain projects, however, this authority may be
delegated. Examples include: (1) delegation of project approval authority by
the Provost to Deans for initiation of projects and for approval of department-funded
projects under $10,000; and (2) delegation of authority by Vice Presidents to
auxiliary enterprises for projects using auxiliary funds.
SCHEDULE
To ensure a priority renovation project is completed by a desired
occupancy date, it must be submitted to Physical Plant with adequate
time to design, competitively bid, and construct the project. To
determine the amount of time a given project requires from a planning
perspective, please refer to the chart below. Previously, October
15 was the deadline to submit renovation projects in order to meet
an August 15 delivery date. Due to the new $2M project budget cap,
the chart below should now be used to estimate project delivery
dates. The timelines shown in the chart are estimates for
each project phase and Physical Plant will make every effort to
complete designated first priority projects within these
time frames. However, these timelines should not be interpreted
as guarantees each specific project schedule will be developed
on the basis of the particular scope and characteristics of that
project. As mentioned previously, new projects involving faculty
recruiting (PARs) are given first priority and may require
that work on existing projects be deferred.
Estimated Design & Construction Schedule for
First Priority Renovation Projects (expressed in calendar days for
each project phase)
| Project Cost
|
Preliminary
Estimate |
Funding Approval
|
Final Design
|
Bid |
Const Duration |
Total Project
Duration |
Total Project
Duration (Months) |
| Up to 250K |
60 |
30 |
60 |
60 |
90 |
300 |
10 |
| $250K 500K |
60 |
45 |
90 |
60 |
120 |
360 |
12 |
| $500K - 1M |
60 |
60 |
120 |
60 |
150 |
450 |
15 |
| $1M - 2M |
60 |
90 |
150 |
60 |
180 |
540 |
18 |
Example: If a project must be completed by August 15, 2003 and
the estimated project cost is $550K, then the work request form
(PP-10) should be submitted to Physical Plant by May 15, 2002 (15
months total time required.)
Clients must recognize the timelines shown in the chart only reflect
the estimated design and construction time required for the project
and do NOT include additional department/unit tasks that may be
required after construction is completed. These commissioning phase
tasks include such things as installation of department purchased
furniture, and special laboratory and/or multi-media equipment,
etc; delivery, installation, and activation of phone and computer
systems; and relocation of occupant files and equipment. These tasks
may add days or weeks to the total project delivery
timelines and must be identified when establishing design and construction
schedules with Physical Plant.
Projects may be submitted at any time and will be added to the
A&E design schedule. The earlier a request is submitted, the
more likely a desired schedule will be met. Projects submitted with
less than the prescribed project timelines may NOT be delivered
by the desired completion date. Departments and non-academic units
are strongly encouraged to work directly with Physical Plant in
managing their workload so that resources may be directed appropriately.
Renovation is a very dynamic activity with many variables and speculative
characteristics. Estimates of cost, resources and schedule are not
exact and become more refined only as the project moves through
the project delivery process. It is therefore of paramount importance
that good communication occurs between Physical Plant and a single
representative from the client organization from the beginning to
the end of the project delivery process. It is equally important
that the clients representative keep all client stakeholders
informed regarding their project.
If you have any questions concerning these procedures or schedules,
please contact John Rishling, Associate Vice President for Campus
Planning and Facilities, at 475-6976.
|