AHTD's Experience with Superpave Pavement Permeability
Through 1997, the Arkansas State Highway and Transportation Department constructed or let to contract approximately 1,700,000 tons of Superpave 37.5 mm, 25 mm and 12.5 mm mix. All of the Superpave designs have been designed on the coarse side of the maximum density line and below the restricted zone. Initial reaction to the mixes dealt with the coarse texture and appearance; however, the pavements performed well and as anticipated. Limited test data on pavement rutting suggests that Arkansass Superpave mixes are less likely to rut than the typical Arkansas Marshall mixes.
After a wetter than normal August 1997, a Superpave project under construction exhibited signs of permeability. Several days after placement of the pavement, a Resident Engineer observed and reported water running from the pavement surface.
A survey of 16 Superpave projects revealed that only two of the sixteen projects showed some signs of permeability. Samples were obtained from each of the 16 projects. Four inch cores were cut at 47 locations for permeability analysis. A falling head permeability apparatus was used to determine the permeability coefficient for each core.
The falling head permeability apparatus was developed by the University of Arkansas as part of the AHTDs Transportation Research Project No. 82, "Asphalt Mix Permeability". TRC 82 evaluated ten Marshall mixes for permeability. The generated permeability data provides a basis for evaluating the permeability of the Superpave projects. The permeability measurements indicated that 60% of the Marshall mixes had permeability coefficient rates greater than 10-4 cm/s. Over time, the Marshall mixes began to close, and the surface began to seal. Permeability dropped. The following permeability categories came from TRC No. 82.
|
Permeability Category |
Permeability Rates |
|
High Permeability |
101 - 10-4 |
|
Low Permeability |
10-4 - 10-6 |
|
Practically Impervious |
10-6 - 10-9 |
For the Superpave permeability analysis, the Research Section and the Materials Division performed permeability and density testing. Correlation of permeability versus lift thickness and permeability versus density was performed. The correlation established the influence that lift thickness and/or density had in predicting pavement permeability. Results are plotted as Figures 1, 2, 3, and 4 respectively. Figure 1 shows the relationship between permeability coefficient and in place air voids. Figure 2 shows the relationship of permeability coefficient and lift thickness. Figure 3 shows the relationship of permeability coefficient versus inplace air voids and lift thickness. Figure 4 shows the lift thickness of the cores used in the analysis.
Figure 1:
Figure 2:
Figure 3:
Figure 4:
The Superpave permeability data and the TRC 82 data support the following conclusions:
k = (1.38 x 10-7)(3.92%AV)(0.61Lift Thickness);
Based upon the data from TRC No. 82 and the Superpave permeability analysis, the recommendations are: