Summary of TxDOT Superpave Projects Constructed in 1997
Introduction
Ten Superpave projects were constructed in 1997 as
part of TxDOT's strategic plan to implement Superpave. Approximately
10,000 mg of Superpave mixture was placed on each of the ten construction
projects. In addition, a minimum of 5,000 mg of conventional
HMAC was placed on each project as control mixtures for comparison
purposes. Eight of the ten projects were built with 19.0mm Superpave
mixtures and the other two were built with Superpave 12.5mm mixtures.
Volumetric mixture designs were completed for each project.
For the most part, the mixture design process was fairly simple.
In some cases, several trial blends were tested in order to be
able to meet the minimum VMA requirements without violating the
VFA requirements.
Construction Experience
The Texas Hot Mix Asphalt Pavement Association (THMAPA)
conducted a survey of the contractors that built the ten Superpave
projects. The results of the survey indicate that constructing
Superpave mixtures appears to be very similar to conventional
hot mix and CMHB mixtures. Tenderness of the mixtures and difficulty
achieving in place density, were the two major concerns expressed
by the contractors. The condition reported by many contractors
and TxDOT employees is the Superpave mix appears to be stable
under the breakdown roller; however, after a few passes of the
breakdown roller, the mix becomes unstable and begins to move
and act much like a tender mix. Further compaction can only be
achieved when the mix has sufficiently cooled to be able to sustain additional
compaction. Mixtures are reportedly tender in a temperature range
of 180F to 270F. Almost all of the 19.0mm mixtures experienced
some degree of tenderness whereas neither of the two 12.5mm mixtures
experienced tenderness. The tenderness experienced with the 19.0mm
mixtures varied from mild to extreme. In a few cases the 19.0mm
mixtures developed numerous micro-cracks and some longitudinal
cracks in the finished mat. In one instance the movement of the
mix under the roller caused the finished mat to be one foot wider
than the placement width.
Production Test Results
Extensive testing was conducted during the mixture
design and production of each project. Four sets of tests were
conducted for each production day. The tests included gradation,
asphalt content, maximum theoretical specific gravity (Rice gravity),
and bulk specific gravity using both the Superpave and Texas gyratory
compactors. Results from the tests indicate that generally, a
good degree of production control was exercised for all the projects.
In addition to the production tests, in-place air voids were
measured on all of the projects. The air voids on seven of the
projects exceeded 10.0%. The in-place air voids on the two 12.5mm
mixtures and the 19.0mm mixture in El Paso were less than 10.0%.
These are the three projects that did not exhibit tenderness
during construction.
Conclusions
- Experience with Superpave 19.0mm mixtures in
Texas indicate that the mixtures can be very tender. As a result,
it is difficult to achieve in-place density on these mixtures.
- Limited experience with Superpave 12.5mm mixtures
indicate that the mixtures are stable under the rollers and in-place
density can be achieved.
- An acceptable level of production control is
achievable on Superpave mixtures.
- There is a good correlation between the densities
of specimens compacted with Superpave compared to Texas gyratory
compactors when plant produced mixtures are compacted.
When compacting laboratory produced mixtures, the
SGC consistently produces mixtures with lower densities than the
TGC.
Recommendations
- Due to the tenderness of the 19.0mm mixtures,
we recommend that construction of 19.0mm mixtures be avoided until
there is a method to predict the "tenderness" phenomena.
- Superpave 12.5mm mixtures should be used when
a Superpave surface is desired until the problems with the 19.0mm
mixtures can be corrected.
- TxDOT should allow either the TGC or the SGC
to be used for field control of HMAC.
Return to Articles about Superpave
Return to Superpave Home Page
Send comments to: Superpave
Project Manager: Robert McGennis
Website Administrator: Clair LaVaye
Graphics by María Saenz
© 1996 The Superpave Center,
The University of Texas at Austin.